RFQ - Q&As
-
Posted August 12, 2022
Posted by:- The Supplemental Forms to be Included with Proposal on Page 5 include Fee Proposal (Appendix B). Appendix B states that it is to be provided to shortlisted firms and submitted in Step Two. Is Appendix B (Fee Proposal) to be included with the RFQ Proposal submitted on August 22nd or on August 25th as Step Two?
- On the CM@Risk Evaluation Form under the Cost Issues section, criteria #7 is “What is the quality of the schedules submitted in the RFQ response?”. We do not find that the RFQ asks for a schedule to be submitted and assume that sample schedules are to be included as part of the RFQ response. Please clarify where you would like to see sample construction schedules included in the RFQ response.
Answer:
- Appendix B is to be submitted as part of Step 2.
- Schedule information is part of Appendix B.
-
Page 24 states, "What is the quality of the schedules submitted in the RFQ response?" - The RFQ doe
Posted by:Appendix B indicates Schedule Start & Completion Date.
-
Page 5 states, "Supplemental forms to be included with Proposal - Fee Proposal - Appendix B"; Page
Posted by:Appendix B should be submitted as part of Step 2. Schedule information is part of Appendix B.
-
Page 3 states, "Submit 4 bound copies"; Page 4 states, "Submit 1 original and 5 copies" - Please ver
Posted by:One original + 5 copies
-
Page 4 states, "Owner will provide a response to questions to all Proposers who have registered with
Posted by:Registration is not required.
-
Question: Page 3 states, "Submit 4 bound copies"; Page 4 states, "Submit 1 original and 5 copies" -
Posted by:Answer: One original + 5 copies.